B.C. Builders Lien Act holdback and lien deadline calculator

On a bigger job, 10% of what you're owed is held back, and if you aren't paid you have 45 days to file a lien. Miss the date and the lien's gone. Put in the completion date and the contract amount, and you'll see the holdback, the day it can be paid and your last day to file.

Work out my dates

Free · No sign-up · Builders Lien Act read 9 November 2026 · General information, not legal advice

Work out the holdback and the dates

Two fields. The answers show as you type, and nothing leaves your phone.

The day the job was substantially finished, or the date on the certificate of completion if one was issued.

The contract price, before GST.

Nothing you type is saved or sent. The math runs on your phone.

Put in the completion date, the contract amount, or both. With a date you get the deadlines; with an amount, the holdback.

B.C.’s Construction Prompt Payment Act isn’t in force yet (checked 9 November 2026). When it starts, the 55 days become 46, and I’ll change this tool the same day.

These are plain calendar dates. If a deadline lands on a Sunday or a holiday, B.C.’s Interpretation Act moves it to the next day that isn’t a holiday; Saturday isn’t a holiday under that Act. Don’t leave a lien to the last day.

General information, not legal advice. For a lien you’re about to file, talk to a lawyer.

Put the holdback on your invoice

Hiring subs? Check their clearance letter

The holdback line

From the day the job's done, counted in calendar days.

Days after completion

  1. Stop 01

    Job complete

    Or the certificate of completion is issued.

  2. Stop 02

    Day 45

    Last day to file a claim of lien.

  3. Stop 03

    Day 55

    The holdback period ends.

  4. Stop 04

    Day 56

    The holdback can be paid, if no lien was filed.

A stop where you step in. Everything else runs on its own.

What is a holdback payment?

Under B.C.’s Builders Lien Act, whoever pays on a contract or subcontract has to keep back 10% of the greater of the work and materials provided or the amount paid. It applies whether you’re paid in stages or at the end. The holdback sits there so anyone further down the line who isn’t paid has something to claim against. When the 55 days are up and no lien has been filed, it’s paid out.

BC Laws: Builders Lien Act, s. 4 and 8 (BC Laws, opens in a new tab) (read 9 November 2026)

When is a job complete under the Act?

“Completed” in the Act means substantially completed, not every last thing. A job counts as done when it’s ready to use, or when what’s left would cost no more than 3% of the first $500,000 of the price, 2% of the next $500,000 and 1% of the rest. If you ask the payment certifier for a certificate of completion, they have 10 days to decide (s. 7). The clock then runs from the certificate.

BC Laws: Builders Lien Act, s. 1 and 7 (BC Laws, opens in a new tab) (read 9 November 2026)

Is B.C.'s Prompt Payment Act in force?

No. The Construction Prompt Payment Act passed in November 2025, but it only starts when the province sets a date by regulation, and none is set. On BC Laws, its sections are marked “not in force” (current to 3 November 2026, read 9 November 2026). When its change to the Builders Lien Act starts (s. 56), the holdback period drops from 55 days to 46, and I’ll update this page and the tool that day.

BC Laws: Construction Prompt Payment Act, SBC 2025 c. 24 (BC Laws, current to November 3, 2026) (BC Laws, opens in a new tab); Bill 20, Construction Prompt Payment Act, as passed third reading, s. 56 (BC Laws) (BC Laws, opens in a new tab). gov.bc.ca: Prompt payment legislation (gov.bc.ca) (gov.bc.ca, opens in a new tab) (read 9 November 2026)

What the calculator does

What it does
Works out the 10% holdback, the last day to file a lien, the day the holdback period ends and the day it can be paid, from the completion date and the contract amount.
Who it's for
Residential contractors and subs in B.C. on jobs where money is held back.
The rule
Builders Lien Act, s. 4: 10% holdback. s. 8: the period ends 55 days after completion. s. 20: file a lien no later than 45 days after completion.
The number
10%, 45 days and 55 days.
What it costs
Free. No sign-up, no email.
What it never does
File a lien, give legal advice, or keep what you type: the math runs on your phone.
Checked
BC Laws, Builders Lien Act (BC Laws, opens in a new tab) (current to 3 November 2026), read 9 November 2026.
Made by
Carver, Maple Ridge, B.C.
Note
General information, not legal advice.

Holdback and lien questions

One-sentence answers, each from the Act itself.

Where every rule comes from

Builders Lien Act sections 1, 4, 5, 7, 8, 15, 20 and 33, and the pages below. General information, not legal advice. BC Laws governs; if a rule changes, I change it here.

  1. Builders Lien Act, SBC 1997 c. 45 (BC Laws, current to November 3, 2026)

    “… must retain a holdback equal to 10% of the greater of … (s. 4) … expires at the end of 55 days after the certificate of completion is issued (s. 8) … may be filed no later than 45 days after the date on which the certificate of completion was issued (s. 20)”

    Checked November 9, 2026

  2. Construction Prompt Payment Act, SBC 2025 c. 24 (BC Laws, current to November 3, 2026)

    “1-46 [Not in force.] … 47-51 [Not in force.] … This Act comes into force by regulation of the Lieutenant Governor in Council.”

    Checked November 9, 2026

  3. Table of Legislative Changes: Construction Prompt Payment Act (BC Laws, to November 3, 2026)

    “Changes Not in Force … 52 to 58 … 2025-24-52 to 58 [conseq] … by reg”

    Checked November 9, 2026

  4. Bill 20, Construction Prompt Payment Act, as passed third reading, s. 56 (BC Laws)

    “Section 8 (1) and (2) is amended by striking out "55 days" and substituting "46 days".”

    Checked November 9, 2026

  5. Prompt payment legislation (gov.bc.ca)

    “The Act received Royal Assent on November 27, 2025, but is not yet in force.”

    Checked November 9, 2026

  6. Interpretation Act, RSBC 1996 c. 238, s. 25, 25.5 and 29 (BC Laws, current to November 3, 2026)

    “If a day that is specified for doing an act falls on a holiday, the day falls on the next day that is not a holiday. … "holiday" includes (a) Sunday, Christmas Day, Good Friday and Easter Monday, …”

    Checked November 9, 2026